Topic 1 : Transparency and governance of natural resources management
Lead Department : The e-Government Unit at the Presidency of Government
Sub-Commitment 1 : Developing a new version of the national open data portal
Milestones
Actions Undertaken
Progress Rate(%)
Drafting the specification and selection of the studies office
– Selection of the studies office in charge of developing the portal;
– Drafting the terms of reference of the portal;
– Drafting the terms of reference of the portal;
100%
Appointing a steering committee and a technical committee to follow up the project
– Prepare a draft decision appointing the steering committee members in charge of the project;
30%
Design and development of the portal
– Development of the first version of the model of the portal;
10%
Testing and put online of the portal
Sub-Commitment 2 : Carrying out an inventory of priority public data in a range of sectors
Milestones
Actions Undertaken
Progress Rate(%)
Identifying priority sectors and announcing the launch of the project
Selection of priority sectors involved in the implementation of the public data inventory project;
100%
Completing the preliminary inventory: presenting the inventory methodology, and launching the inventory activities at the level of the sectors involved
– Organization of a workshop in November 2021 for the benefit of the ministries to present the public data inventory project and set the methodology for its implementation;
– Organization of working meetings with ministries have been selected to implement the inventory project, such as the Ministry of Equipment, the Ministry of Economy and Planning, and the Ministry of religious affairs;
– Organization of working meetings with ministries have been selected to implement the inventory project, such as the Ministry of Equipment, the Ministry of Economy and Planning, and the Ministry of religious affairs;
100%
Assessment and follow-up of public structures in the open data inventory process
– Organization of meetings with some ministries to follow-up the implementation progress of the data inventory;
– Completion of the initial version of the public data inventory within a number of ministries involved;
– Completion of the initial version of the public data inventory within a number of ministries involved;
20%
Validation of the final inventory document and publication of some datasets included in it